NatureWorks announces key milestones for PLA expansion in Thailand 

June 6, 2021
Energy & Chemical Value Chain

NatureWorks LLC (Minnetonka, Minn.) announced the completion of key milestones in their global manufacturing expansion plan for a new fully integrated Ingeo polylactic acid (PLA) production facility that is anticipated to open in Thailand by 2024, subject to shareholder approval. When fully operational, the new plant will have an annual capacity of 75,000 tons of Ingeo biopolymer and will produce the full portfolio of Ingeo grades.

Last week, the Thailand Board of Investment announced its approval of the NatureWorks manufacturing project that will be located at the Nakhon Sawan Biocomplex (NBC) in Nakhon Sawan province. The NBC is the first biocomplex project in Thailand established in accordance with the government’s bioeconomy policy.

NatureWorks recently completed the front-end engineering design work with Jacobs. Jacobs was selected and managed in partnership with IAG, who provided front-end project management and project controls. Final detailed engineering is currently underway, and NatureWorks expects to announce further details on the new facility later this year.

“We are pleased to share these significant accomplishments as part of our next phase for global manufacturing expansion,” said Rich Altice, President and CEO of NatureWorks. “The approval and support from the Thailand Board of Investment was a critical milestone on our path toward opening our new facility in Thailand. With both the recently announced capacity expansion at our facility in Blair, Nebraska and this new manufacturing complex, we can further address the global market demand for sustainable materials and continue leading the development of high-performance applications that capitalize on Ingeo’s unique material properties.”

The new manufacturing complex will include production for lactic acid, lactide, and polymer making it the world’s first polylactide facility designed to be fully integrated. NatureWorks will build and operate all three facilities, having both process and energy integration to increase efficiency of the manufacturing operation dedicated to Ingeo biopolymer production.

In 2002, NatureWorks became the first company to produce PLA biopolymers at commercial scale. In 2013, NatureWorks expanded its flagship Blair, NE facility to an annual total capacity of 150,000 metric tons, making it the largest PLA manufacturing plant in the world. NatureWorks also completed a portfolio of enhancements to the Blair site enabling the plant to establish a new record production level in 2019.

By Mary Page Bailey

Source: chemengonline.com

comments closed

Related News

May 4, 2024

Heikki Malinen appointed as the President and CEO of Neste Corporation

Energy & Chemical Value Chain

Neste Corporation’s Board of Directors has appointed Heikki Malinen, M.Sc. (Econ.), MBA (Harvard) as the President and CEO of Neste as of 2 November 2024, at the latest. Malinen joins Neste from Outokumpu Corporation where he has held the position of President and CEO since 2020.

May 4, 2024

Rossouw to step down as Sasol CFO in October

Energy & Chemical Value Chain

Petrochemicals company Sasol has announced that CFO and executive director Hanré Rossouw will step down from his position, effective October 31. Sasol has started the process to appoint a successor. Rossouw will still oversee the publication of Sasol’s reports for the financial year ending June 30, to allow for a structured handover period.

May 4, 2024

Chemours CFO Jonathan Lock resigns following code of ethics violations

Energy & Chemical Value Chain

Chemours announced its CFO Jonathan Lock has resigned from all positions within the company, according to an SEC 8-K filing on April 23. The resignation comes in the aftermath of the company announcing that Lock, former CEO Mark Newman, and principal accounting officer Camela Wisel, had been placed on administrative leave.

How can we help you?

We're easy to reach