Borealis pulls out of $6.8bn plan to build petrochemical plant in Kazakhstan

May 22, 2020
Energy & Chemical Value Chain

Austrian polyolefins and fertilizers producer Borealis has scrapped plans to build a multi-billion-dollar polyethylene (PE) facility in Kazakhstan’s Atyrau Region, citing economic uncertainties sparked by the coronavirus (COVID-19) pandemic.

The decision not to go ahead with the 1.25mn tonne/yr installation, announced on May 19, is another blow to energy export dependent Kazakhstan, already struggling with the collapse in hydrocarbon prices. Petrochemical projects that could produce value-added products from the Central Asian nation’s vast gas and oil resources are seen as offering the country potential to diversify away from over-reliance on the export of raw commodities.

The project was drawn up as a 50:50 joint venture with Kazakh state-owned United Chemical Company (UCC). Borealis first announced the project in 2018. The facility was to include a cracker that would process cheaply sourced Kazakh ethane gas feedstock and two PE units that would function with Borealis’ proprietary Borstar technology.

“Thorough assessment”

“The decision to discontinue this project is based on a thorough assessment of all aspects of the prospective venture and impacted by the effects of the COVID-19 [coronavirus disease 2019] pandemic as well as the increased uncertainty of future market assumptions,” Borealis said.

UCC had estimated the total investment figure for the petrochemical project would be $6.8bn.

At the same time that it signed the agreement for the PE facility, Borealis, in 2018, also inked a memorandum of understanding (MoU) to cooperate in realising a 500,000 tonne/yr polypropylene (PP) project with Kazakhstan’s Samruk-Kazyna Sovereign Wealth Fund. Borealis told Chemical Week that its statement on pulling out of the PE project did not also relate to the PP plan.

Philippe Roodhooft, executive vice president/Middle East and growth projects at Borealis, told Chemical Week that the cracker would have had an annual capacity of 1.2mn tonnes fed by ethane from the giant Tengiz oil and gas field. In turn, the cracker was to feed a PE complex based on two third-generation Borstar-process units. The project was planning to target the CIS region’s markets, but to also include some exports beyond that region.

Alfred Stern, CEO of Borealis, and Mark Tonkens, CFO, earlier in May announced plans to cut costs to curb the impacts of the coronavirus pandemic on the firm’s balance sheet. The measures included reducing capital expenditure by 25% to €750mn in 2020.

By: Kanat Shaku

Source: BNE

comments closed

Related News

April 26, 2024

CIECH Group will change its name to Qemetica in June

Energy & Chemical Value Chain

We are closing the chapter of the Chemicals Import Export Headquarters, and opening a new chapter under the name of Qemetica – a chemical group driving many industries on all continents. Therefore, the change of name is also accompanied by the adoption of the key goals of the business strategy for the next 6 years. – says Kamil Majczak, President of the Management Board.

April 26, 2024

Neste annouces first success in processing pyrolysis oil from discarded tires

Energy & Chemical Value Chain

In its efforts to advance chemical recycling, Neste has successfully conducted its first processing trial run with a new challenging raw material, liquefied discarded tires. In the processing run, Neste produced high-quality raw material for new plastics and chemicals.

April 26, 2024

Sika opens synthetic fibers production facility in Peru

Energy & Chemical Value Chain

Sika is opening a state-of-the-art facility in Lima, Peru, to produce synthetic macro fibers, and expanding the rollout of a product range with great growth potential in Latin America. With this innovative technology, Sika is further strengthening its position as a leading supplier to the mining industry and a strong partner for infrastructure projects.